A PCB order is rarely late because of the assembly line. It is late because four separate stages were quoted as if they were one, and the buyer planned around a single number that described only one of them.
This page sets out the four stages separately, with the times we quote for each, so the schedule can be built from what actually happens rather than from an average.

| Stage | What it covers | Typical time |
|---|---|---|
| 1. Quotation | Gerber, BOM and pick-and-place reviewed; DFM issues raised | Same day to 1 working day |
| 2. Bare board fabrication | Drilling, plating, imaging, solder mask, surface finish | 24 hours to 16 days, by layer count (table below) |
| 3. Component procurement | Sourcing the BOM from authorised distributors | In stock to 16+ weeks, by part |
| 4. Assembly and test | SMT, through-hole, AOI, X-ray, functional test | About 7 days, counted from the day all materials are on site |
Only stage 4 is a fixed number. Stages 2 and 3 are quoted separately because they behave differently: fabrication scales with layer count, procurement scales with which parts are on allocation.
| Layers | Prototype, quick turn | Prototype, standard | Mass production (above 30 m²) |
|---|---|---|---|
| 2 layers | 24 hours | 3–4 days | 8–10 days |
| 4 layers | 48 hours | 5–6 days | 10–12 days |
| 6 layers | 72 hours | 6–8 days | 12–14 days |
| 8 layers | 72 hours | 8–10 days | 14–16 days |
The difference between quick turn and standard is not effort, it is queue position. A quick-turn order displaces other work on the same line, which is why the price differs as much as the date does.
| Order conditions | Standard delivery | Fastest delivery |
|---|---|---|
| Prototype (under 20 pcs) | 2 days | 8 hours |
| Small volume (20–100 pcs) | 3 days | 12 hours |
| Medium volume (100–1,000 pcs) | 6 days | 24 hours |
| Mass production (above 1,000 pcs) | Depends on BOM | Depends on BOM |
All assembly times are counted from the day all materials are on site.
Fabrication is a known quantity: a 6-layer board takes 6 to 8 days on a standard schedule, and that number does not move. Procurement is not. On any BOM there are usually two or three lines that decide the delivery date, and they are rarely the expensive parts:
This is why we review the BOM at quotation rather than after the order: the parts that decide the date can usually be identified in an hour, and a qualified alternative found at that point costs nothing. Found after the order, it costs the schedule.
Can a 6-layer board really be assembled in seven days?
The seven days covers assembly and test only, counted from the day materials are on site. Bare board fabrication for a 6-layer standard order is 6 to 8 days, and the two stages can overlap only if boards are ordered ahead of components.
What makes a quick-turn order possible?
Queue priority on the line, not a faster process. The same equipment runs the same recipe; a quick-turn order simply goes to the front, which is why it carries a premium.
What do you need to quote an accurate lead time?
Gerber files, the BOM with manufacturer part numbers, and the quantity at each stage. With those three, the four stages can be quoted separately and honestly instead of being compressed into one optimistic number.